PMP Project Management Professional 2024 past questions and answers

This 2024 PMP Project Management Professional set has 29 practice questions. Try these 5 free sample questions, tap a question to reveal the answer and explanation. Then practise the whole 2024 set with instant marking.

Practise the full 2024 setTimed exam mode

Sample PMP Project Management Professional 2024 questions

1. A product team using Scrum has missed its sprint goal for two consecutive sprints. The team says urgent requests from a senior manager repeatedly interrupt planned work. What should the project manager do first?
  1. Escalate the senior manager's behavior to the sponsor and request disciplinary action.
  2. Facilitate a team discussion to understand the interruptions and agree on a transparent way to protect sprint focus while keeping stakeholders informed.
  3. Require the team to add overtime to recover the missed sprint work.
  4. Move all urgent requests into the product backlog without discussing them with the product owner.

Answer: B. Facilitate a team discussion to understand the interruptions and agree on a transparent way to protect sprint focus while keeping stakeholders informed.

The project manager should enable the team to surface the impediment and agree collaboratively with the product owner and stakeholders on handling changes. Escalating or imposing overtime before understanding the cause undermines self-management and does not resolve the interruption pattern.

2. In a predictive project, a stakeholder asks for an additional reporting dashboard that is not in the approved scope baseline. The dashboard is estimated to add two weeks and has a clear business benefit. What should the project manager do?
  1. Ask the team to begin work because the benefit is clear.
  2. Add the dashboard to the scope statement and update the baseline without further review.
  3. Document the request and submit it through the integrated change control process for impact analysis and decision.
  4. Reject the request because scope cannot change after the baseline is approved.

Answer: C. Document the request and submit it through the integrated change control process for impact analysis and decision.

A requested scope change should be documented, assessed for impacts, and decided through the defined change control process before the baseline or work is changed. Immediate implementation bypasses governance, while baselined scope is not inherently immutable.

3. On a hybrid infrastructure project, a technical lead wants a highly resilient design while the operations lead favors a less costly design that is easier to support. Their disagreement is delaying a decision. What is the best initial action for the project manager?
  1. Bring both leads together to clarify constraints and interests, then facilitate a fact-based comparison of options against agreed project objectives.
  2. Choose the design preferred by the more senior lead.
  3. Ask the sponsor to decide before the team has examined the trade-offs.
  4. Separate the leads and assign each a different design to implement in parallel.

Answer: A. Bring both leads together to clarify constraints and interests, then facilitate a fact-based comparison of options against agreed project objectives.

Collaborating helps the parties understand underlying interests and reach a solution using project criteria. Choosing by rank or starting competing implementations avoids resolving the conflict and may waste resources.

4. A predictive project is four weeks behind its critical path because a specialist activity has taken longer than estimated. The sponsor asks for a recovery plan that does not reduce required quality. What should the project manager do first?
  1. Shorten every remaining activity by the same percentage.
  2. Remove quality inspections from the critical path.
  3. Add resources to every activity, regardless of whether they are resource-constrained.
  4. Analyze the critical path and feasible crashing or fast-tracking options, including their cost, risk, and quality impacts.

Answer: D. Analyze the critical path and feasible crashing or fast-tracking options, including their cost, risk, and quality impacts.

Schedule compression should target the critical path and be evaluated for cost, risk, and quality consequences. Across-the-board shortening and removing inspections are not evidence-based recovery strategies.

5. During a review of a hybrid project, the project manager learns that a proposed data-transfer method may violate a new privacy regulation in one operating region. The compliance team has not yet assessed the design. What should the project manager do?
  1. Continue the design because the regulation was introduced after project approval.
  2. Pause the potentially affected transfer decision, engage compliance and legal experts, and assess required changes and impacts.
  3. Ask the vendor to accept responsibility for regulatory compliance in the contract.
  4. Wait until deployment testing to determine whether the transfer method is allowed.

Answer: B. Pause the potentially affected transfer decision, engage compliance and legal experts, and assess required changes and impacts.

The project must assess applicable regulatory obligations with qualified experts and address compliance before proceeding with a potentially noncompliant design. Delegating responsibility to a vendor or waiting until testing does not remove the organization's obligation.

More PMP Project Management Professional years

2026202520232022

All PMP Project Management Professional years · PMP subjects

PassSpark questions are original practice questions written to each exam's syllabus and format, in the style of past questions. They are not official past papers and are not affiliated with JAMB, WAEC, NECO, any university or any exam body.