1. A manufacturer uses activity-based costing. Annual set-up costs of £180,000 are driven by 60 batches, while inspection costs of £120,000 are driven by 240 inspections. Product R is made in 30 batches and requires 80 inspections during the year. What overhead cost should be assigned to Product R?
- £120,000
- £150,000
- £130,000
- £100,000
Answer: C. £130,000
Set-ups: £180,000 × 30/60 = £90,000. Inspections: £120,000 × 80/240 = £40,000, giving £130,000. The main distractor £150,000 incorrectly allocates inspection costs using batches rather than inspections.
2. A factory makes a product that sells for £480 per unit. Direct material is £180 per unit and is the only cost treated as variable under throughput accounting. Each unit uses 30 minutes of the bottleneck resource. The factory's operating cost is £120 for each hour the bottleneck is available. Using throughput accounting ratio = throughput per bottleneck minute ÷ operating cost per bottleneck minute, what is the ratio?
- 5.0
- 4.0
- 2.5
- 7.5
Answer: A. 5.0
Throughput per unit is £480 − £180 = £300, or £10 per bottleneck minute. Operating cost per minute is £120/60 = £2. The ratio is £10/£2 = 5.0; using all production costs as variable would understate throughput.
3. A company needs 4,000 components. Making each component would use materials costing £14, labour costing £8 and variable overhead of £3. A further £6 of fixed overhead is allocated per unit but would continue whichever option is chosen. A supplier offers the components for £27 each. There is no alternative use for the capacity. Which decision minimises relevant cost, and by how much in total?
- Buy; save £8,000
- Make; save £8,000
- Buy; save £24,000
- Make; save £24,000
Answer: B. Make; save £8,000
Relevant make cost is £14 + £8 + £3 = £25 per unit; the unavoidable allocated fixed overhead is irrelevant. Buying costs £27, so making saves £2 × 4,000 = £8,000. Including the £6 allocated fixed cost would wrongly favour buying.
4. A business has 2,000 machine hours available, and machine hours are the only limiting factor. Product M earns contribution of £48 per unit and uses 2 machine hours. Product N earns contribution of £40 per unit and uses 1.25 machine hours. Demand for both products exceeds the available capacity. Which product should be prioritised to maximise contribution?
- Product M, because it earns the higher contribution per unit
- Either product, because both earn positive contribution
- Product M, because it uses more machine hours per unit
- Product N, because it earns the higher contribution per machine hour
Answer: D. Product N, because it earns the higher contribution per machine hour
M earns £48/2 = £24 per machine hour; N earns £40/1.25 = £32 per machine hour. N should be prioritised. Comparing contribution per unit, rather than per limiting-factor hour, gives the wrong ranking.
5. A company is deciding whether to launch a service. If demand is high (probability 0.6), the launch will earn £80,000; if demand is low (probability 0.4), it will lose £20,000. Rejecting the launch gives a certain profit of £32,000 from an alternative use of resources. Using expected monetary value, what should the company do?
- Reject the launch; its expected value is £32,000
- Launch; its expected value is £56,000
- Launch; its expected value is £40,000, which exceeds £32,000
- Reject the launch; the possible loss makes the launch's expected value negative
Answer: C. Launch; its expected value is £40,000, which exceeds £32,000
Launch EMV = (0.6 × £80,000) + (0.4 × −£20,000) = £40,000, which exceeds the certain £32,000 alternative. The £56,000 distractor omits the probability-weighted loss outcome.